You need to set up the new service request completion process.

Which two components should you include in the solution? Each correct answer presents a complete solution. NOTE: Each correct selection is worth one point.
A . connection reference
B . business process flow
C . Power Automate flow
D . connection

Answer: AC

Explanation:

Reference: https://docs.microsoft.com/en-us/power-apps/maker/data-platform/create-connection-reference