Which two command sequences must be configured on a switch to establish a Layer 3 EtherChannel with an open-standard protocol? (Choose two.)
Which two command sequences must be configured on a switch to establish a Layer 3 EtherChannel with an open-standard protocol? (Choose two.)
A . interface GigabitEthernet0/0/1
channel-group 10 mode auto
B . interface GigabitEthernet0/0/1
channel-group 10 mode on
C . interface port-channel 10
no switchport
ip address 172.16.0.1 255.255.255.0
D . interface GigabitEthernet0/0/1
channel-group 10 mode active
E . interface port-channel 10
switchport
switchport mode trunk
Answer: DE
Latest 200-301 Dumps Valid Version with 489 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Question or answer is wrong.
If L3 EC then C and D are correct.
The question needs to be L2 EC for D and E to be correct.