As the Sprint Planning meeting progresses, the Development Team sees that the workload is greater than they can handle.
Which two are valid actions? (Choose two.)
A . Recruit additional Development Team members before the work can begin.
B . The Development Team ensures that the Product Owner is aware, starts the Sprint, and monitors progress.
C . Cancel the Sprint.
D . Remove or change selected Product Backlog items.
E . The Development Team works overtime during this Sprint.
Answer: BD