Which two activities take place during Team Breakout #1 on the first day of Program In-crement (PI) Planning? (Choose two.)

Which two activities take place during Team Breakout #1 on the first day of Program In-crement (PI) Planning? (Choose two.)
A . Risks on the teams’ planning boards are resolved by the Release Train Engineer
B . Teams use color-coding for their backlog items as a reminder that they are re-quired to have all backlog item types on their planning boards
C . Draft objectives and uncommitted objectives are written
D . All teams’ planning boards are visible and use the same color-coding
E . Draft objectives are written but do not include exploration Enablers

Answer: C,D