A solution architect has finished conducting interviews and gathering requirements for a company, and has determined that the logical requirements are:
• two data centers for high availability
• synchronous replication to meet the zero minute RPO
• separating management workloads from application workloads
• dedicated 10Gb uplink for each low latency server
• single management port for the entire environment
Which two actions would meet the design requirements? (Choose two.)
A . Create two data center objects in vCenter Server.
B . Configure vSAN Stretched Clustering.
C . Configure SR-IOV for low latency servers.
D . Create one folder for Management workloads and one folder for application workloads.
Answer: BC