A solution architect has finished conducting interviews and gathering requirements for a company, and has determined that the logical requirements are:
• two data centers for high availability
• synchronous replication to meet the zero minute RPO
• separating management workloads from application workloads
• dedicated 10Gb uplink for each low latency server
• single management point for the entire environment
Which two actions would meet the design requirements? (Choose two.)
A . Configure 1 Port Group with a dedicated 10Gb Uplink for low latency servers.
B . Deploy two clusters, one for management workloads and one for application workloads.
C . Build 2 Port Groups, one for management serves and one for application servers.
D . Install two vCenter Servers in Enhanced Link Mode.
Answer: BD
Latest 3V0-624 Dumps Valid Version with 123 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund