You need to create a plan that meets the following requirements:
• Migrate the data to the new system.
• Implement a standardized method for creating items.
• Prevent items from being created in different ways going forward.
Which two actions should you recommend? Each correct answer presents a complete answer. NOTE: Each correct selection is worth one point.
A . Migrate item data in the cutover plan after the annual updates of items,
B . Suggest creating a Power Bl report to identify like-items after migration.
C . Migrate items in the cutover plan before the annual update of items.
D . Suggest a Master Data Management team who standardizes the item master.
E . Migrate existing items as-is.
Answer: B,D