Which two actions should you perform?

You need to set up reordering for new items.

Which two actions should you perform? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.
A . Create one coverage group for raw materials and one for finished goods.
B . Set the item coverage manual flag on the warehouse to Yes.
C . Create separate coverage groups for raw materials, finished goods, and retail packaging.
D . Set the item coverage manual flag on the warehouse to No.
E . Create one coverage group for retail packaging items and another for items in the warehouse

Answer: CD

Explanation:

Reference: https://docs.microsoft.com/en-us/dynamics365/supply-chain/master-planning/coverage-settings