Team morale is at an all-time low after an incident involving one of the team members.
Which two actions should the project manager take to resolve the situation? (Choose two)
A . Host a special meeting to talk about what happened.
B . Escalate the issue to human resources (HR).
C . Review the lessons learned document with the team.
D . Conduct a team-building workshop.
E . Discuss this incident in the project review meeting.
Answer: B,C