Which two actions should Employee1 perform?

Employee 1 needs to set up the new items for the product line

Which two actions should Employee1 perform? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.
A . Create new finished goods and release to the legal entity
B . Create new raw materials and release to the legal entity.
C . Create new finished goods with predefined variants and release to the legal entity.
D . Create new finished goods and release to the legal entity. Raw material products are not required for these items.
E . Create new raw materials with variants and release to the legal entity.

Answer: B,C