Which two actions should a project manager consider while launching a new virtual team? (Choose two)
Which two actions should a project manager consider while launching a new virtual team? (Choose two)
A . Recruit the best resources within the organization to be part of the virtual team
B . Evaluate the project manager’s own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls
C . Identify the types and quantities of resources required for each work package or activity
D . Establish in the beginning, how progress will be monitored and the best means for communicating progress
E . Verify if team members are on more than one team and cannot devote enough time to this team
Answer: D,E