Which two actions are completed in the Implement phase of the SES Complete Implementation framework? (Select two)

Which two actions are completed in the Implement phase of the SES Complete Implementation framework? (Select two)
A . Presentation of the SES Complete Solution Proposal
B . Execution of a Pilot Deployment
C . Implementation of the Solution Configuration Design
D . Preparing a customized high-level project plan
E . Gathering of business drivers and technical requirements

Answer: BC

Explanation:

In the Implement phase of the SES Complete Implementation framework, two key actions are typically executed:

Execution of a Pilot Deployment: This action is crucial to test the solution in a controlled subset of the customer environment, ensuring that the solution design meets functional and security requirements before a full-scale rollout. The Pilot Deployment validates configurations and allows adjustments as needed based on real-world performance.

Implementation of the Solution Configuration Design: This involves setting up and configuring all aspects of the solution according to the predefined Solution Configuration Design. This step ensures that all features and functionalities are properly implemented, configured, and aligned with the solution’s objectives.

Explanation of Why Other Options Are Less Likely:

Option A (presentation of the SES Complete Solution Proposal) and Option D (preparing a project plan) are tasks completed earlier in the planning phase.

Option E (gathering of business drivers and technical requirements) is part of the Assess phase, where requirements are collected and documented.

Thus, Pilot Deployment and Solution Configuration Design implementation are the correct actions for the Implement phase.