Which two (2) elements can an administrator include when building a resource target in the Computers blade of the IT Management Views? (Select two.)
Which two (2) elements can an administrator include when building a resource target in the Computers blade of the IT Management Views? (Select two.)
A . Resource filters
B . Data classes
C . Resource associations
D . Organizational groups
E . Filter criteria
Answer: A,E