Which time fields are used during forward scheduling in material requirements planning? There are 2 correct answers to this question.

Which time fields are used during forward scheduling in material requirements planning? There are 2 correct answers to this question.
A . Scheduling Margin Key
B . Total Replenishment Lead Time
C . Goods Receipt Processing Time
D . Processing Time for Purchasing

Answer: C,D