Which time elements are considered during backwards scheduling for planned orders? Note: There are 3 correct answers to this question.

Which time elements are considered during backwards scheduling for planned orders? Note: There are 3 correct answers to this question.
A . Goods receipt processing time
B . Opening period
C . Quality inspection time
D . Goods issue processing time
E . In-house production time

Answer: A, B E