Which three questions might be answered by Development Team members at the Daily Scrum? (Choose three.)
A . How is the Sprint proceeding?
B . What did I do yesterday that helped the Development Team meet the Sprint Goal?
C . Why were you late?
D . What will I do today to help the Development Team meet the Sprint Goal?
E . How many hours did I spend on the project yesterday?
F . What will I be working on tomorrow?
G . Do I see any impediment that prevents me or the Development Team from meeting the Sprint Goal?
Answer: B,D,G