You are verifying multipathing from the host to the storage controller.

Which three components should you verify? (Choose three.)
A . Verify that all switch ports connected to the hosts and storage devices are online using the vendor’s GU
C . Verify that both FC HBA ports in the host are online using the HBA vendor’s GU
E . Verify that the FC HBAs WWNN’s are in the igroup in the SV
G . Verify that the SVM’s LIFs being used for multipathing are attached to the correct same physical FC port.
H . Verify that the storage controller FC target ports status are online with the switch port showing the FC switch to which they are connected.

Answer: ADE