Which three actions should you perform in sequence?
DRAG DROP
A company that uses discreet manufacturing concepts to produce solar panels has a temporary change of glass supplier. The substitute glass will only be used for three months. The company also uses Bill of materials (BOM) version to track changes of the raw materials.
Managers are manually adjusting the production picking lists to reflect the alternate glass that is being temporarily used. The time spent doing manual adjustments to production picking lists has become a burden.
You need to create a new BOM with the alternate glass and include a from and to date on the BOM version.
Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Answer:
Latest MB-320 Dumps Valid Version with 141 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund