You need to set up the metal production route and BOM.
Which three actions should you perform? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.
A . Set the operation route type as Standard.
B . Set the input warehouse on the resource to the vendor warehouse.
C . Set the operation route type as Vendor.
D . Set all BOM lines warehouse to the production warehouse.
E . Set all the BOM lines to resource consumption.
Answer: B,C,D