Which the following statement regarding networks are correct?

Project Structures

Which the following statement regarding networks are correct? Note: there are 3 correct answers for this question.
A . If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.
B. You can assign more than one activity element to a network activity.
C. Capacity requirements of a network activity are reduced when the activity is confirmed.
D. During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity.
E. You can assign the same work center to more than one activity on the same network.

Answer: B,C,E