Which technique will help the project manager to accelerate the deliverable?
After the second iteration of a component development project, the project team conducts a retrospective It shows that in the initial phase the project has failed to comply with a product functionality. The planning for this product has a predominantly predictive approach.
Which technique will help the project manager to accelerate the deliverable?
A . Impact mapping
B . Rolling wave planning
C . Collective code ownership
D . Scrum of Scrums
Answer: B
Latest PMP Dumps Valid Version with 721 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Answer B..Rolling wave planning is the ideal way to address unclear/evolving/changing project requirements.