The business analyst has completed the requirements gathering and documentation processes in developing a baseline document. Several signoffs are needed During the joint review process with the key stakeholders, the stakeholders announce that they are still not ready to sign off due to a communication gap.
Which technique should the business analyst have followed to ensure consensus?
A . The business analyst should have reviewed the requirements of the project sponsor first before reviewing other requirements.
B . The business analyst should have performed a complete review of each requirement with one of the stakeholders’ peers before the meeting
C . The business analyst should have performed a complete review of each requirement with the key stakeholders prior to the meeting.
D . The business analyst should have invited the key stakeholders to the meeting.
Answer: C