Which technique could the business analyst use to manage requirements?

A business analyst is working on a highly complex project and has elicited a large number of requirements from stakeholders in several departments Due to the large number of requirements, the stakeholders have determined that they would like to prioritize them to minimize a potentially large scope.

Which technique could the business analyst use to manage requirements?
A . SMART goals
B . RACI models
C . MoSCoW
D . Storyboarding

Answer: C

Latest PMI-PBA Dumps Valid Version with 200 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments