Which technique consists of review meetings to determine if the stakeholders agree that their needs are being met with the identified requirements?
A . Risk analysis
B . Prototyping
C . Stakeholder management
D . Structured walkthrough
Answer: D
Explanation:
Structured walkthroughs are meetings that help determine if the stakeholders agree that their needs are being met with the identified requirements.
Answer. A is incorrect. Risk analysis reviews identified risks in the requirements to determine the probability and impact of the risk event.
Answer. B is incorrect. Prototyping is used to gain user agreement with the proposed solution and requirements for the solution.
Answer. C is incorrect. Stakeholder management is not a technique that is used as part of validating requirements.