An organization’s lead times and the flow of tasks across value streams are being impacted because tasks often sit waiting in queues.
Which technique can be used to overcome this challenge?
A . Clarifying definition of done’
B. Introducing a push system
C. Increasing batch sizes
D. Limiting work-in-progress
Answer: D