Which team member do you contact to verify the project plan and manage expectations for the release schedule?

You notice that the scope of your project exceeds the original estimates, and the Minimum Lovable Product (MLP) might not be delivered on time.

Which team member do you contact to verify the project plan and manage expectations for the release schedule?
A . Project delivery leader
B. Scrum master
C. Lead business architect
D. Deployment architect

Answer: A

Explanation:

The project delivery leader is responsible for managing the project scope, timeline, budget, and quality. They also communicate with the stakeholders and sponsors to align expectations and resolve issues. If the scope of the project exceeds the original estimates, the project delivery leader should be contacted to verify the project plan and manage expectations for the release schedule.

References: https://academy.pega.com/library/81/pega-certified-business-architect-pcba-81

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments