Which tasks are typically performed by a tester on an Agile project?
1) Implementing test strategy.
2) Documenting business requirements.
3) Measuring and reporting test coverage.
4) Coaching development team in relevant aspects of testing.
5) Executing test-driven development tests.
A . 2, 5
B. 2, 4, 5
C. 1, 3, 4
D. 1, 3
Answer: B
Latest CTFL-AT Dumps Valid Version with 40 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund