Which task should be performed?

A customer has restarted the MCS service on their Avamar server to apply a configuration change made in the mcserver.xml file. The daily scheduled backups have not started, although they can connect successfully to the Avamar Administrator.

Which task should be performed?
A . Restart the backup scheduler
B . Verify that GSAN service is running
C . Restart the MCS service
D . Verify that the garbage collection is not running

Answer: A