Which steps in the Value Stream should be the main focus when prioritizing improvement items?

Which steps in the Value Stream should be the main focus when prioritizing improvement items?
A . Steps with a high activity ratio
B. Steps with short process time and short lead time in the future-state map
C. Steps with long lead time and short process time in the current-state map.
D. Steps with a long process time

Answer: C

Explanation:

https://www.scaledagileframework.com/identify-value-streams-and-arts/