Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?
A . Capture
B . Examine
C . Propose
D . Decide
Answer: B
Explanation:
In the issue and change control procedure within PRINCE2, the "Examine" step involves considering alternative options to address an issue that is being managed formally. This step is crucial for evaluating the possible responses to an issue before making a decision on the best course of action.
Reference: PRINCE2 Foundation manual, PRINCE2 official resources