A . Planned revenue requires a sales order assigned to a WBS element
B. Planned revenue can be transferred from a sales quotation
C. Actual revenue is posted via a billing plan assigned to a WBS element
D. Actual revenue is posted via a billing document created from a sales order

Answer: B,C