Which statements are correct? (More than one answer is true.)
A . You cannot assign an individual inspection plan to each inspection type and status.
B . The status profile stipulates a sequence for inspection lot processing.
C . A further goods receipt for the material and delivery is only possible for the model lot if the usage decision was “OK”.
D . A further goods receipt for this material/vendor is not possible if the model inspection has not been completed.
E . The inspection lots can be processed simultaneously.
Answer: BD