You are using WBS elements and activities are NOT assigned.
Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question
A . You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"
B . You can always maintain the actual start if the WBS element has the status "Released"
or "Partially released"
C . You can always maintain the actual start and finish date of a WBS element
D . You can only maintain the actual start of a WBS element if the finish date is not maintained
Answer: A,D