Which statement is true about the SAFe backlog model?
A . Capabilities are in the Program Backlog
B. Features are in the Program Backlog
C. Stories are in the Solution Backlog
Answer: B
Explanation:
Features are present in Program Backlog and Stories are present in Team backlog.