Exam4Training

Which statement is true about estimating and forecasting the Portfolio Backlog?

Which statement is true about estimating and forecasting the Portfolio Backlog?
A . Feature estimates are rolled up into Epic estimates
B. Refinement is necessary when estimating the effort needed to implement an Epic
C. WSJF is used to assign Epics to Value Streams

Answer: A

Latest SAFe-RTE Dumps Valid Version with 120 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version