Which statement is true about estimating and forecasting the Portfolio Backlog?

Which statement is true about estimating and forecasting the Portfolio Backlog?
A . Feature estimates are rolled up into Epic estimates
B . Refinement is necessary when estimating the effort needed to implement an Epic
C . WSJF is used to assign Epics to Value Streams

Answer: A