Which statement is correct when planning maintenance work that is to be carried out by an external company?
A . In the control key assigned to the order operation, the "Service"indicator must always be activated.
B. A service master record must always be assigned to the external order operation.
C. If you assign a control key with indicator "Service" for an external service, you have to enter the actual values via the service entry sheet.
D. If you assign a control key for an external order operation, the actual values must always be entered as a goods receipt in the system.
Answer: C