Which statement explains the target ‘be on time and hit deadlines’ for flexible delivery?

Which statement explains the target ‘be on time and hit deadlines’ for flexible delivery?
A . It reduces testing in order to meet deadlines
B. It sets the project baseline at the correct level
C. It enables team dynamics to remain the same
D. It improves the supplier’s reputation with the customer

Answer: A

Explanation:

Reference: https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_41