Which statement explain when a Product Backlog item is considered "Done"?

Which statement explain when a Product Backlog item is considered "Done"?
A . When the Product Owner declares it to be "Done".
B. When the Development team agrees that it is "Done".
C. When it is potentially releasable.

Answer: C

Explanation:

A Product Backlog items has to be potentially releasable. This should be covered by the Definition of Done.