Which statement explain when a Product Backlog item is considered "Done"?
Which statement explain when a Product Backlog item is considered "Done"?
A . When the Product Owner declares it to be "Done".
B. When the Development team agrees that it is "Done".
C. When it is potentially releasable.
Answer: C
Explanation:
A Product Backlog items has to be potentially releasable. This should be covered by the Definition of Done.
Latest PSPO-I Dumps Valid Version with 481 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments