Which statement describes how the PRINCE2 ‘starting up a project’ process can be applied in an agile environment?

Which statement describes how the PRINCE2 ‘starting up a project’ process can be applied in an agile environment?
A . PRINCE2 is predictive, but not emergent
B. PRINCE2 is predictive and can be emergent
C. PRINCE2 requires a lengthy start to a project
D. PRINCE2 requires a disruptive start to a project

Answer: B