Which statement best describes the Sprint Backlog as the output of the Sprint Planning? (Choose the best answer)

Which statement best describes the Sprint Backlog as the output of the Sprint Planning? (Choose the best answer)
A . Every item has a designated owner.
B . It is ordered by the Product Owner.
C . Each task is estimated in hours.
D . It is the Developers plan for the Sprint.
E . It is a complete list of all work to be done in a Sprint.

Answer: D