Which statement about the ‘protect the level of quality’ target is CORRECT?

Which statement about the ‘protect the level of quality’ target is CORRECT?
A . It is achieved by allowing enough time for testing
B . It is achieved by using the same team members
C . It gives confidence on the progress of the project
D . It delivers the early realization of benefits

Answer: D

Explanation:

Reference: https://publications.axelos.com/prince2agile2016/content.aspx?showNav=true&expandNav=true&page=PRA_41#:~:text=PRINCE2%20Agile%20protects%20the%20level,the%20quality%20level%20is%20met

Subscribe
Notify of
guest
1 Comment
Inline Feedbacks
View all comments
Alexa
Alexa
2 years ago

In my opinion the answer should be A.
PRINCE2 Agile protects the level of quality and ensures that deadlines are met by reducing the amount delivered by the project but not reducing activities that ensure that the quality level is met.

delivering early realization of benefits is about being on time and meeting deadlines.