Which statement about the Directing a Project process is true?
A . Provides a mechanism for the Project Board to assure that there is continued business justification
B . Covers the day-to-day activities of the Project Manager
C . Ensures there are regular progress meetings
D . Begins on completion of the Initiating a Project process
Answer: A
Explanation:
The Directing a Project process in PRINCE2® provides the Project Board with a mechanism to ensure there is continued business justification for the project throughout its lifecycle. This process is crucial for maintaining the project’s alignment with organizational objectives and for making decisions at key points such as stage boundaries.
Reference: PRINCE2® Foundation official documentation and study materials.