Exam4Training

Which stakeholder of a project team is responsible to provide closeout documentation to the client? Architect

Which stakeholder of a project team is responsible to provide closeout documentation to the client? Architect
A . Authority
B. Having Jurisdiction (AHJ)
C. Construction Manager
D. ICT Distribution Designer/Project Manager

Answer: D

Exit mobile version