Which stakeholder of a project team is responsible to provide closeout documentation to the client? Architect
Which stakeholder of a project team is responsible to provide closeout documentation to the client? Architect
A . Authority
B . Having Jurisdiction (AHJ)
C . Construction Manager
D . ICT Distribution Designer/Project Manager
Answer: D