Which stakeholder approves a project’s result?

Which stakeholder approves a project’s result?
A . Customer
B . Sponsor
C . Seller
D . Functional manager

Answer: A

Latest PMP Dumps Valid Version with 721 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments