SRDF/Metro has been deployed between two data centers. SRDF/Metro is operating normally. Maintenance tasks at the R1 data center require the array to be offline.

Which SRDF operation should be executed on the Metro RDF pairs to facilitate the planned outage without affecting application I/O?
A . Failover
B . Split with bias set to R2
C . Suspend with bias set to R2
D . Swap

Answer: A