You need to use your resource cost effectively with a certain minimum use, even if it means producing more than demand.
Which solutions would apply to this scenario? Note: There are 2 correct answers to this question.
A . Capacity leveling will be possible for production and storage resources.
B . Balance can be achieved between excessive prebuild and minimum use by incorporating violation costs.
C . Excess stock can be generated and will need to be staged in an overflow warehouse.
D . Minimum capacity utilization will result in pull production occurring.
Answer: B C