Which solution would apply to this scenario?
While modeling for a large machine with high capital needs, you need it to run cost effectively with minimum utilization, even if it means producing more than demand .
Which solution would apply to this scenario? Note: There are 2 correct Answers to this question.
A . Capacity leveling will be possible for production and storage resources.
B . Excess stock can be generated and will need to be staged in an overflow warehouse.
C . Enough demands can be pulled forward and pull production will occur.
D . Balance can be achieved between excessive prebuild and minimum utilization by incorporating violation costs.
Answer: C,D